Changing a Single-AZ Task to a Dual-AZ Task
DRS allows you to change a single-AZ task to a dual-AZ task, improving task reliability while remaining the original task.
Constraints
- A dual-AZ task cannot be changed to a single-AZ task.
- Only tasks in the Incremental, Incremental failed, or Paused state can be changed.
- Only synchronization tasks from GaussDB Primary/Standby to Kafka can be changed.
Procedure
- Log in to the management console.
- Click
in the upper left corner and select a region and project.
- Choose Databases > Data Replication Service. The Data Replication Service page is displayed.
- On the Data Synchronization Management page, select the target task and choose More > Change to Primary/Standby in the Operation column.
- On the displayed page, select the standby AZ. If the task is over a public network, you need to specify the EIP of the standby task and click OK.
- After submitting the change, click Back to Task List. On the Data Synchronization Management page, the task status is Changing to primary/standby.
After the task type change is complete, you can check that the parent task has two subtasks: one primary task and one standby task.
Parent topic: Task Life Cycle
- Constraints
- Procedure